HomeMy WebLinkAbout04 WRRTC_Minutes_04-04-2025_ApprovedWRRTC APRIL 4, 2025 MEETING MINUTES – APPROVED MAY 9, 2025
1
Wisconsin River Rail Transit Commission
Commission Meeting – Friday April 4, 2025 at 10:00 am
1. 10:00 AM Call to Order – Marty Krueger, Chair
2. Roll Call. Establishment of Quorum – Dan Hauck, Admin
Crawford
Carl Orr, 1st Vice Chair X
Jefferson
Mary Roberts X
Mark Gilberts Excused John Kannard, Vice Secretary X
Tom Cornford Excused Jeff Smith X
Dan Herbst, Alternate Excused
Dane
Kevin Potter X
Rock
Dave Homan, 2nd Vice Treasurer X
Jeff Huttenburg, Treasurer X Tom Brien X
Jim Bolitho X Kevin Stone X
Grant
David Wiederholt X
Sauk
Brian Peper X
Mike Lieurance X Gaile Burchill X
Robert Scallon, 2nd Vice Chair Excused Marty Krueger, Chair X
Tim McCumber, Alternate Excused
Green
Harvey Kubly, 1st Vice Treasurer Excused
Walworth
Al Stanek Excused
Larry Kranig Excused Richard Kuhnke, 2nd Vice Secretary Excused
Mark Gundlach X Allan Polyock Excused
Iowa
Charles Anderson, Secretary X
Waukesha
Rick Beutler, 3rd Vice Treasurer Excused
Kate Reimann X Richard Morris X
Craig Hardy X Karl Nilson Excused
Commission met quorum.
Others present for all or some of the meeting:
• Jamaar Benton, WSOR
• Benjamin Mohlke, WisDOT
• Ken Lucht, WSOR
• Don Vruwink, OCR
• Alan Anderson, Pink Lady RTC
• Dan Hauck, SWWRPC
3. Action Item. Certification of Meeting’s Public Notice – Noticed by Admin.
Motion to approve meeting’s public notice – Brien/Smith. Passed Unanimously.
4. Action Item. Approval of Agenda – Prepared by Admin.
Motion to approve the agenda as posted – Brien/Smith. Passed Unanimously.
5. Action Item. Approval of draft March 7, 2025 Meeting Minutes – Prepared by Admin.
Motion to approve the March 7, 2025 meeting minutes as presented. Anderson/Lieurance. Passed Unanimously.
6. Updates. Public Comment – Time for public comment may be limited by the Chair.
Al Anderson reintroduced himself to the commission and noted that Pink Lady RTC meets three times a year in Sauk County.
Ken introduced Jamaar Benton, sales manager for WSOR, who has been with WSOR for 7 years.
7. Updates. Announcements by Commissioners
Homan reported that he and Bolito toured WSOR’s engine facility. Hardy reported that the Iowa County public works committee postponed the
discussion of withdrawal from the commission to the May 5th meeting, and the committee has prepared several questions for Krueger and Lucht in
advance. Peper reported that he is now a commissioner of the Pink Lady RTC.
REPORTS & COMMISSION BUSINESS
8. WRRTC Financial Report – Treasurer
• Motion to approve the February 2025 Treasurer’s Report as presented. Anderson/Orr. Passed unanimously.
• Motion to pay invoice to SWWRPC for 1st quarter management in the amount of $8,750 and WSOR for the Merrimac Bridge in the
amount $173,049. Morris/Reimann. Passed Unanimously.
WRRTC APRIL 4, 2025 MEETING MINUTES – APPROVED MAY 9, 2025
2
• Budget adoption timeline and process. Draft budget in May with public hearing and adoption in June. Needs to be adopted by August
1, 2025.
9. Wisconsin & Southern Railroad’s Report on Operations – Lucht, WSOR
Lucht reported that WSOR worked with WisDOT on several grant applications submitted in February, including a tie replacement project on the
Reedsburg Subdivision from Devils Lake to Reedsburg, which remains a top priority; WSOR will provide carload data to support the application, with
hopes for a 2025 award. Another priority is the continuous welded rail project between Wauzeka and Boscobel, where environmental concerns
make rail modernization critical. WSOR plans to continue work east into Iowa County, with full modernization of the Prairie Subdivision identified as
a systemwide priority; the Prairie Subdivision has the highest defect rate in the WATCO system and is 20 years overdue for upgrades. The 2025
capital plan, which includes replacement of 30,000 maintenance ties, has been shared with commissioners. WSOR noted that although the Fox Lake
Subdivision south of the state line cannot receive state funds, there is ongoing investment; maintenance ties are being installed on the Reedsburg
Subdivision. On the Monroe Subdivision, 24,000 ties will be installed in Green and Rock Counties to maintain track classification, and 21 grade
crossings will be updated. The B298 bridge in Boscobel received a state grant, and design plans will be presented to the City of Boscobel. WSOR is
also coordinating with Farm City Elevator on state approval and working with UW Extension in Waukesha and Jefferson Counties on an updated
systemwide economic impact study, with a proposal expected before the May meeting. Lucht also shared WSOR’s economic profile, as requested at
the March meeting. Benton spoke about community outreach and transloading opportunities, encouraging commissioners to engage with counties
and potential customers.
10. WisDOT Report – Mohlke – WisDOT.
Mohlke reported that peer review and quality control efforts are ongoing, and a ribbon-cutting event is being planned for the Merrimac Bridge. The
next focus will be the Janesville Bridges project; however, inflation is expected to increase overall project costs. To help address these rising costs,
the scope of work has been reduced. Mohlke also noted that new FRIP loans have been approved for Farm City Elevator in Brodhead to support the
construction of a new grain silo.
11. Permits / Licenses
TDS Telecom, Dane County, City of Fitchburg, Utility Permit. Motion to approve utility permit for TDS Telecom in City of Fitchburg. Orr/Homan.
Passed unanimously.
12. Walking Iron Trail, Dane County – Huttenburg / Bolitho
Huttenburg reported that 15 sections of rail remain, with ties relocated to the Fuchs Trucking area; nearly 70% of the ties have been removed, and
the project is nearing completion. Huttenburg expressed satisfaction with the progress and quality of work. Bolitho noted that the corridor is nearly
ready for construction, with Dane County currently having access and only a few remaining items needing removal.
13. Walking Iron Trail, Dane County – Interim Trail Use Agreement – Potter
Motion to approve re-execution of Interim Trail Use Agreement between WisDOT, Dane County, and WRRTC. Brien/Reiman. Passed unanimously.
14. Administrator’s Report – Hauck
SWWRPC is currently updating the interactive and static maps for all rail transit commissions and will provide the maps when they are complete.
15. Adjournment.
Motion to Adjourn at 11:08 am. Peper/Burchill. Passed Unanimously.